Network Map
Loading the live map around Central Híbrida de Tômbwa…

Central Híbrida de Tômbwa

Substation5 MWENDE Cuanza SulCuanza Sul, Angola

Start Free

Overview

Central Híbrida de Tômbwa is a 5 MW substation on the ENDE Cuanza Sul network in Cuanza Sul, Angola. Technology: solar;diesel; operated by Empresa Pública de Produção de Electricidade, E.P. (PRODEL, EP). It is located at about 15.774° S, 11.917° E.

Key Facts

Type
Substation
Network
ENDE Cuanza Sul
Operator / Owner
Empresa Pública de Produção de Electricidade, E.P. (PRODEL, EP)
Capacity
5 MW
Technology
solar;diesel
Commissioned
2018
State / Province
Cuanza Sul
Country
Angola
Coordinates
15.774° S, 11.917° E
Layer
Substations
Asset ID
17775640

More Attributes

Barrier
fence
Landuse
industrial
Plant method
photovoltaic;combustion
Power
plant

Nearby Substations